City Edge Estate, Bendigo

Villawood Properties

"Boutique subdivision development" 

  • 10 week duration
  • Approx 6 team members onsite at peak period
  • Works completed on time and on budget as per tender
Project stats
  • Earthworks
  • Gabion walls with timber seating
  • Jute matting 
  • Tube stock planting 
  • Establish trees 
  • Grass seeding
  • Asphalt walking trials
  • Exposed aggregate concreting
  • Concrete hardball court with line marking and goal rings
  • Design & construct train playground
  • Picnic shelter, pedestrian bridge & viewing platform
  • Retention basins 
  • 12 months maintenance
Total $232,000